POSTED: 01:30 a.m. HST, Oct 15, 2008
Answer: Okada Trucking Co. is reconstructing a failing retaining wall that supports the sidewalk and roadway.
It was given the go-ahead to begin the $745,000 city project on July 14, but because of "some contract language clarification," the work did not start right away, said Eugene Lee, director of the city Department of Design and Construction.
The contract specifies a 150-calendar-day schedule and it's up to the contractor to finish within that time frame, he said.
The contract completion date is targeted for Dec. 10, subject to extension for unforeseen conditions and/or weather delays.
Lee explained that access through Mid-Pacific Institute's baseball field, below the retaining wall, was needed for heavy equipment to install the foundation of the new wall.
After discussions with Mid-Pacific, a right-of-entry was obtained, with a specific window to start and complete the work established so as to not interfere with the school's baseball season, he said.
The city then set the July 14 "Notice To Proceed" date for the contractor in order to comply with the time restriction.
Lee said that any time work is done on or around a road, "the impacts to traffic are always a concern."
"While we do our best to mitigate these, there are times when shutting down parts of the road is unavoidable," he said. "In these situations, we ask for the public's patience and understanding."
In addition to reconstructing the retaining wall, the project involves replacing affected sidewalks, curbs, gutters and asphalt pavement; constructing new wheelchair ramps; installing new crosswalks; and replacing street markings, signs and traffic signals.
Question: What is the construction work going on at the corner of University Avenue and Maile Way? Why wasn't it completed before the fall semester started? It is making a real mess of traffic into Manoa Valley. It would have been a way smaller mess if done during the summer when the student count at the University of Hawaii was far smaller.
Answer: Okada Trucking Co. is reconstructing a failing retaining wall that supports the sidewalk and roadway.
It was given the go-ahead to begin the $745,000 city project on July 14, but because of "some contract language clarification," the work did not start right away, said Eugene Lee, director of the city Department of Design and Construction.
The contract specifies a 150-calendar-day schedule and it's up to the contractor to finish within that time frame, he said.
The contract completion date is targeted for Dec. 10, subject to extension for unforeseen conditions and/or weather delays.
Lee explained that access through Mid-Pacific Institute's baseball field, below the retaining wall, was needed for heavy equipment to install the foundation of the new wall.
After discussions with Mid-Pacific, a right-of-entry was obtained, with a specific window to start and complete the work established so as to not interfere with the school's baseball season, he said.
The city then set the July 14 "Notice To Proceed" date for the contractor in order to comply with the time restriction.
Lee said that any time work is done on or around a road, "the impacts to traffic are always a concern."
"While we do our best to mitigate these, there are times when shutting down parts of the road is unavoidable," he said. "In these situations, we ask for the public's patience and understanding."
In addition to reconstructing the retaining wall, the project involves replacing affected sidewalks, curbs, gutters and asphalt pavement; constructing new wheelchair ramps; installing new crosswalks; and replacing street markings, signs and traffic signals.